Framing is going well, first level is almost complete. No thanks to the rainiest August on record (thanks a bunch mother nature) They're set to start framing the second level this week. It's quite exciting seeing the house take shape.
August 23, 2010
And up go the walls
We're so proud of the skilled craftsman she's becoming....
Framing is going well, first level is almost complete. No thanks to the rainiest August on record (thanks a bunch mother nature) They're set to start framing the second level this week. It's quite exciting seeing the house take shape.
Framing is going well, first level is almost complete. No thanks to the rainiest August on record (thanks a bunch mother nature) They're set to start framing the second level this week. It's quite exciting seeing the house take shape.
August 8, 2010
A solid base
Foundation is almost done. After some setbacks due to the heaviest rain of the year (we weren't quite ready for the swimming pool just yet), we're hoping for better weather this week to keep on track. Backfill should happen in the next couple days and then we'll be set to start framing.
July 27, 2010
Digging a hole
Now that's what you call cheap labour (it only took her 2 days!)...excavation went smoothly and is complete. The foundation work will start in the next couple days. Soon we'll have a basement.
July 21, 2010
And we're off!
Look at us closing a city road...we apologize to the residents of Queensdale. Digging started today (finally). They're hooking up to the services so the road had to be cut. Should start breaking ground on our lot shortly. Thank you Luciano!
July 12, 2010
It's a go....
We have a lot